Item Coversheet
ALAMOSA CITY COUNCIL
COUNCIL COMMUNICATION


Subject/Title:

Motion authorizing an additional $241,075 for the Victoria Street Drainage Infrastructure project.

Recommended Action:

Staff recommends that Council authorize an additional $241,075 for the completion of the storm water collection project.


Background:

Victoria Street and the surrounding area have historically flooded during a heavy rain event. This is largely due to the existing undersized storm water infrastructure.  Victoria Street is the collection point for a large area and much of it is impermeable. In the spring of 2019, Reynolds Engineering was hired to assess the area and provide options that would resolve this issue.

 

In July of 2019, Reynolds Engineering provided 4 options to consider all of which would alleviate the buildup of storm water.  Each option included a summary of the work and a cost estimate. Due to the complicated nature of the project, Options 1, 2, and 3 were estimated around $1,350,000 while Option 4 was estimated at $740,000. However, Option 4 required the City to obtain land for a detention pond. Staff felt that option 4 was the best solution so long as we were successful in purchasing the land needed for the detention pond.

 

On July 17, 2019 in an executive session, staff presented all 4 options to Council along with the recommendation to move forward with Option 4 and requested authorization to pursue the vacant land needed for the detention pond. Council approved the request along with the budget, and we were successful in purchasing the vacant lot adjacent to the college Heights Baptist Church in February of 2020.

 

Once the property was secured, Reynolds Engineering had clear direction on where the storm water would be stored and could begin the design of Victoria Storm Drainage project. Reynolds submitted the completed design and construction documents for approval in the spring of 2021. With the expectations of the work being completed in the summer of 2022, the City went through a formal bid process receiving only one qualified bid from RMS Utilities for the amount of $774,044.75. The RMS bid, plus the other expenses already incurred to complete the project are listed below. The total project budget is now $1,064,075, which remains below the other options with 2019 cost projections.

 

RMS Utilities                        $774,044

Property purchase               $107,000

Lift Station equipment         $123,031

Detention blocks                  $ 20,000

Fencing                                $ 25,000

Contingency                        $ 15,000

 

Until recently, the original approved budget would have been adequate for this project. However, the volatility of the construction labor and material market has led to substantial cost increases. An example on how much the market has changed is a contractor could purchase and install a 15” storm water pipe for $27 per linear foot in 2019. Today, that cost is about $70 per linear foot – a 160% increase. Staff does not believe that rebidding the project will result in a lower price. Most contractors are currently booked and are not taking on additional large-scale projects and the higher material costs would be consistent for them as well.
Issue Before the Council:

Does Council wish to authorize an additional $241,075 to the budget to complete the Victoria St drainage infrastructure?


Alternatives:

1)    Approve the requested increase to the budget.

2)    Re-bid the project in hope of additional bidders with lower prices.

3)    Decline to approve the request and provide staff with further direction.



Fiscal Impact:

The additional cost will be paid out of the Enterprise Fund or offset with ARPA funds depending on the inflation impact on other planned projects and the 10-year projected fund balance.  If approved, the amount will be included in the first budget amendment for the 2022 annual budget.


Legal Opinion:
City Attorney will be available for questions.

Conclusion:

A solution to the drainage problem on Victoria and neighboring streets is a high priority. This needs to be in place prior to the rebuilding of Victoria Street in 2023. The budget increase is necessary to complete the project and move forward.